Picture gallery: Development of the ELBE center for high power radiation sources



9/2012 Shielding completed

innen_jan12

10/2011 Connecting the buildings ...

innen_oct



innen_oct

9/2011

innen_sept

8/2011 Anschluss an Beschleunigerhalle

innen_august



innen_august

7/2011 Innenausbau - Strahlenschutzbunker

innen_juli

7/2011 Außenanlage (Baubeginn Hochfeldlabor)

aussen_hochfeld

2/2011 Richtfest

richtfest

2/2011

richtfest

12/2010

steel



steel

11/2010 Steel construction

steel

10/2010 End wall reconstruction

autumn

9/2010

basement

7/2010

basement

5/2010

parkinglot2

2/2010 Preparation of the construction area for the new ELBE /PW building (size of the present parking lot)

parkinglot

1/2010 Footprint of the planned building

footprint



URL of this article
https://www.hzdr.de/db/Cms?pOid=30350


Contact

Prof. Dr. Ulrich Schramm

Director Institute for Radiation Physics and Head Laser Particle Acceleration Division
u.schrammAthzdr.de
Phone: +49 351 260 2471