Data Acquisition Manual: How to run Neutron Time of Flight Measurements at nELBE
- Inelastic Scattering Experiment to measure Photon Production Cross Sections -
(previous version up to Oct. 2016)
DAQ preparations:
To run neutron inelastic scattering measurement you first have to do some preparations:
| 1. | Switch on the electronics: | |||||||
switch on
|
(see here) | |||||||
| 2. | Switch on the detectors: | |||||||
| login to FWK21 (HV control PC) | rdesktop -g 1240x900 -a 16 -k de fwk21 user name: ntofdaq password: ********** |
|||||||
| switch on the detectors you want to use (cf. cabeling scheme) | start "isegCANHVControl" via desktop shortcut | |||||||
| use Ortec 660 voltage supplies in NIM crate 2 of rack 3 to switch on HPGe detectors | (see here) | |||||||
| 3. | Start MBS (2x): |
|||||||
| login to RIO4-1 for LaBr3 DAQ and to RIO4-2 for HPGe DAQ |
user name: ntofdaq |
|||||||
| go to working directory |
|
|||||||
| start MBS prompter | mbs | |||||||
| initialise MBS | @start | |||||||
| 4. | Set MBS initialisation parameters: | |||||||
| login to FWKDAQ1 (in another terminal window) | ssh -X ntofdaq@fwkdaq1 password: *********** |
|||||||
| go to working directory |
|
|||||||
| open setup.ini for text editing if you want to do some special settings |
xemacs setup.ini & | |||||||
| or open setup_short.ini for text editing if you want to change only the important special settings |
xemacs setup_short.ini & | |||||||
| 5. | Start scaler output program (2x): | |||||||
| login to RIO4-1 for LaBr3 DAQ and to RIO4-2 for HPGe DAQ |
user name: ntofdaq |
|||||||
| start shm2file (if doesn't work do a "sta acq"-"stop acq" in MBS first) | ./shm2file | |||||||
| 6. | Open MBS monitoring windows (2x): | |||||||
| login to FWKDAQ1 (in another terminal window) | ssh -X ntofdaq@fwkdaq1 password: *********** |
|||||||
| go to working directory |
|
|||||||
| open mbsprint.l and mbs_scaler.l for monitoring (each in its own terminal window) |
tail -f mbsprint.l tail -f mbs_scaler.l |
|||||||
| 7. | Start RFIO server and client: | |||||||
| login to ZIRKONIA | ssh -X ntofdaq@zirkonia password: *********** |
|||||||
| go to directory rawDispRFIO output | cd rawDispRFIO | |||||||
| start RFIO dispatcher | rawDispRFIO | |||||||
| In MBS: connect to RFIO Server (2x) |
connect rfio zirkonia -disk |
|||||||
| 8. | Start monitor DAQ and monitoring windwos for ELBE Operators: | |||||||
| see Monitor DAQ manual | ||||||||
Running the DAQ:
Now the measurement can be started. This has to be done in the MBS prompter (prm):
|
||||||||||||||||||||||||||||||
If any problem occurs:
| Problem | Solution | ||||||||||||
|
|
||||||||||||
|
|
||||||||||||
|
|
||||||||||||
|
|
||||||||||||
|
|
||||||||||||
|
|
||||||||||||
|
|

